Main Menu

change a weight?

Started by Benahmed Abdelkrim, April 08, 2016, 05:23:01 PM

Previous topic - Next topic

0 Members and 1 Guest are viewing this topic.

Benahmed Abdelkrim

  Sometimes we need to improve some of the tables produced by the program,  to adjust and modify the weight of its value set, for example, starting from 95% to 99%. So we get the best and tables but time account.
    The purpose of this presentation is it possible to change the relative weight at one time for all time      constraints, not as we do now is a per constraint one by one  ?

sorry for my bad english
B.A/krim

Liviu Lalescu

Yes, you can change all weights with a single click, in "min days between activities constraints dialog" or with the "spread activities evenly over the week".

Benahmed Abdelkrim

 thinks, it works very well... :)
B.A/krim