FET Support (English) => General Stuff => Topic started by: Guido on September 13, 2010, 11:25:33 PM

Title: Changing activities order
Post by: Guido on September 13, 2010, 11:25:33 PM
Is it possible to change the order followed by FET when it generates a timetable ? I have a trouble with a teacher who has a lot of activities with the same class and I'd like to generate his timetable for first because otherwise FET doesn't close the timetable.
Title: Re: Changing activities order
Post by: Liviu Lalescu on September 14, 2010, 04:36:44 AM
You can do that if you change the FET code.

Another possibility, easier: FET will schedule firstly the fixed activities. So, you can fix the activities of this teacher and generate.
Title: Re: Changing activities order
Post by: Hagai on September 17, 2016, 08:05:43 PM
1. Which file is the file to chnge its code?
2. when you write "fixed" you mean ....
Hagai
Title: Re: Changing activities order
Post by: Liviu Lalescu on September 17, 2016, 08:31:45 PM
With newer FET, you can do this from the program. Unlock "Enable group activities in initial order", then add such some "group activities in the initial order" items. You can read the Help there for instructions.

If you still want the answer to the previous questions:

1. src/engine/generate_pre.cpp.
2. with a constraint activity preferred starting time attached to the activity.
Title: Re: Changing activities order
Post by: Volker Dirr on September 17, 2016, 09:14:31 PM
i think it will be easier if you do:
fet -> advanced -> group activities in the initial order
then select all activities of that teacher