Hello, I have just started using FET and I have a question. In stead of giving the teachers a maximum number of hours per day to teach, we give the teachers a maximum number of per week.
How do I create that constraint?
Thank you
In FET, the exact number of hours per week is entered by the user, through the activities of that teacher. FET generates a weekly schedule, with max days per "week" = 35.
Where is it entered? Does it need to be typed directly into the data file?
I have looked and I cannot find it, before posting this I did a forum search on the word "week."
When you enter the activities of that teacher, the number of hours per week = sum of duration of the activities for that teacher.
"sum of duration of the activities for that teacher" that is not in my version.
Is that the same as Data > Time Constraints > Teachers > "A teacher works in an hourly interval max days per week"
I am using Version: 5.19.0 (January 2013) in OSX in English
No. When you enter 5 activities, each with duration 1, the teacher will have 5 hours per week.