I read the topic about the split activities and the generation of rooms
So I tried to assign an activity to a room, but in the dialog box no consistent activity appears. For instance, if I select a Teacher I expect to see the activities where he's involved in, but this is not the case. Also, when I try to assign a subject to a room there is a problem I do not know, maybe due to the translation, if I assign a subject to the preferred room or assign the preferred subject for the room as written (does this make sense?)
This is the first step actually. I should have shown this one first
I tried to match activities and classrooms which seems to work. What is the best way, assign a subject or all activities of this subject?
How do I get simultaneous activities ? For example I made an activity English with three teachers as the class will be divide into three groups regarding their level low medium and high. I might have a problem with the basic teacher constraint...?
I am sorry to ask those question, but I'm a little bit in a hurry and new in that school without Headmaster...
and working at weekends as you can see
:-[
For second picture: the "Filter" thing will show you the constraints which satisfy this filter. If you want to add a new constraint, you have to select them in the add constraint dialog (filter is one thing, add constraint dialog is another thing).
For first picture: yes, it is a wrong translation. Could you please tell me how to write "subject preferred room"? Is it "salle preferee pour la matiere"? Please write me with correct accents.
QuoteI tried to match activities and classrooms which seems to work. What is the best way, assign a subject or all activities of this subject?
How do I get simultaneous activities ? For example I made an activity English with three teachers as the class will be divide into three groups regarding their level low medium and high. I might have a problem with the basic teacher constraint...?
I am sorry to ask those question, but I'm a little bit in a hurry and new in that school without Headmaster...
and working at weekends as you can see
:-[
If you use subject preferred room or activity preferred room, the things are equivalent. Only that you need to enter less constraints for subject preferred room (a subject represents more activities).
No, you do not have any problem with the basic teachers constraints. Just watch the number of hours for each teacher, to be all right.
QuoteFor second picture: the "Filter" thing will show you the constraints which satisfy this filter. If you want to add a new constraint, you have to select them in the add constraint dialog (filter is one thing, add constraint dialog is another thing).
For first picture: yes, it is a wrong translation. Could you please tell me how to write "subject preferred room"? Is it "salle preferee pour la matiere"? Please write me with correct accents.
Yes that's right
Salle préférée pour la matièreWhen this all will be over I'll send you some additional translations
by the way
save isn't
sauver but enregistrer.
save as should be e
nregistrer sousMany many thanks for your support
Do we have to assign all the sub activities as well?
I mean, when we define an activity Maths for instance the total 5 hours might be divided into 4 periods, 3 times 1 hour and one period of two consecutive hours. The program indent those sub activities. Do we have to assign the classroom 4 times ?
Yes, unfortunately in your case. I wanted to give the user complete independence.