FET Support (English) => Get Help => Topic started by: yahi on October 30, 2015, 05:51:47 AM

Title: two activities the same day
Post by: yahi on October 30, 2015, 05:51:47 AM
good morning 
though i chose  the  constraint min days  between  activities  the time table still generates two similar  activities  in the  same  day. how  to  overcome  such a problem .............thanks
Title: Re: two activities the same day
Post by: Liviu Lalescu on October 30, 2015, 06:58:34 AM
Make the constraint have weight 100% (not 95%).