Hi. I'm newbie on this forum and with FET, sow - plesae don't be angry on me :)
Problem is that I want to set subject one per day. I don't want situation like that f.e.: class 5a has too maths am Monday. I want that f.e. class 5a (this class has 4 maths per week) has only one math per day.
How can I do it?
Thanx for any advice :)
Add a larger activity, split into 4. The minimum days between each pair of activities should be 1, weight 100% (not default, 95%), any boolean value for consecutive if same day (because it is never applied).
Or, if Math activities are A1, A2, A3, A4, add a constraint min n days between activities, for A1, A2, A3, A4, min 1 days, weight 100%, any boolean value for consecutive if same day.