Hello
I am back :)
so I should start from the beginning
QuoteFET-5.7.0 released
09/29/08 at 12:52:41
ChangeLog:
- Added an advanced command to spread better the divided activities in a week - very useful for schools and high-schools, probably.
Deos the spread function have any use in the Alfaromeo custom version which has 12 days ?
Welcome back! :-)
Maybe you could try the spreading from official, to see what it does.
It is useful if you have activities split into 2 per week and want minimum days between them to be 2. Also, if you have 3 activities per week, you may want them not consecutive.
I think it cannot be used on your custom version, because minimum 2 FET days means maybe minimum 1 real day.
Hello Liviu
and thanks for reply
I am used with spread funtion in official version
Now I want to try it for custom version..but, given your reply, it seems impossible
Thanks