من فضلكم هل يمكن اضافة قيد : ادنى حصص يومية مع وسم للمدرس ؟
شرح السبب لعلي اجد حلا آخر :
احتاجه في التعامل مع الحصص الفردية التي نتحصل عليها عند تدوير التكنلوجيا في الطور الثانوي الجزائري
مثلا : استاذ الفيزياء يدرس حصتين تكنلوجيا +حصة فيزياء في الفصل الاول ، في الفصل الثاني يعفى من التكنلوجيا فتبقى حصة الفيزياء منفردة
Indeed, I neglected to adapt this constraint from the official FET. Do you mean teacher activity tag min hours daily per real day? It is difficult, but should be done. If not now, I will add your suggestion in the TODO list.
Also, maybe you could use activities occupy min time slots from selection, but this one does not allow empty slots; you can specify the exact day, add all the activities of that teacher, and the occupied min number.
I am not sure I understood exactly your situation and reasons.
Quote from: Liviu Lalescu on August 04, 2021, 06:56:24 PM
Indeed, I neglected to adapt this constraint from the official FET. Do you mean teacher activity tag min hours daily per real day? It is difficult, but should be done. If not now, I will add your suggestion in the TODO list.
Also, maybe you could use activities occupy min time slots from selection, but this one does not allow empty slots; you can specify the exact day, add all the activities of that teacher, and the occupied min number.
I am not sure I understood exactly your situation and reasons.
thank you for your response
the reason:
whene i have a teacher teaching 2 Subject("A","B") , if he have in one day 3 hours (2hours" A" and 1hour B) , but the problme is A it is a semestriel subject so in the second semester the teacher bechom teaching only 1 hour in that day !
so with the new constraint i will use it to conferm "B" allways 2 hours in each day
if there is an other solution tell me
Thank you [/left]
You are welcome!
So, for half (FET) days, and with allow empty days?
Quote from: Liviu Lalescu on August 04, 2021, 07:23:53 PM
You are welcome!
So, for half (FET) days, and with allow empty days?
thank you
yes, i use mornings/aftermorinigs Mode
No, I meant, the constraint min 2 activities with tag per half day? (as opposed to real day)? And allowing empty days?
Quote from: Liviu Lalescu on August 04, 2021, 07:32:46 PM
No, I meant, the constraint min 2 activities with tag per half day? (as opposed to real day)? And allowing empty days?
Yes, per half day and allowing empty days
thank you
You are welcome!
I propose you a custom version just for you. Let me know if you are interested.
I would not like to add it into the official, at least for now, because I think some people would like for the real day, and also because it is a bit risky.
Quote from: Liviu Lalescu on August 04, 2021, 07:57:35 PM
You are welcome!
I propose you a custom version just for you. Let me know if you are interested.
I would not like to add it into the official, at least for now, because I think some people would like for the real day, and also because it is a bit risky.
yes , i am interested
thank you very much
OK, I will try and let you know if and when I did it.
I managed to do it: https://lalescu.ro/liviu/fet/download/custom/kaddour-khin/
Please report bugs. I hope I got everything right.
Quote from: Liviu Lalescu on August 04, 2021, 09:49:31 PM
I managed to do it: https://lalescu.ro/liviu/fet/download/custom/kaddour-khin/
Please report bugs. I hope I got everything right.
Thank you
i will try with it, and tell you the result
Quote from: Liviu Lalescu on August 04, 2021, 09:49:31 PM
I managed to do it: https://lalescu.ro/liviu/fet/download/custom/kaddour-khin/
Please report bugs. I hope I got everything right.
thank you very much , this is exactly what i need
i try it many times and it work verry well !!
i really appreciate that
You're welcome!
I just released the new official FET-6.1.2 version with this implemented. Thank you for the suggestions!
Quote from: Liviu Lalescu on August 08, 2021, 11:07:42 AM
I just released the new official FET-6.1.2 version with this implemented. Thank you for the suggestions!
Thank you very much Mr Liviu Lalescu
You're welcome! :)