FET Forum

FET Support (English) => Get Help => Topic started by: ngoctp29121982 on August 20, 2022, 03:35:18 AM

Title: Min Days
Post by: ngoctp29121982 on August 20, 2022, 03:35:18 AM
Hello Liviu.
I have a small question: Why does FET not allow users to set the minimum number of days between a group of lectures to 0 directly on the software?
Title: Re: Min Days
Post by: Liviu Lalescu on August 20, 2022, 07:23:05 AM
When you add the activity, add 0 and the min days between activities constraint will not be added. Or remove this constraint if you added with 1 min days. Or make the weight 0% (but this is different).
Title: Re: Min Days
Post by: ngoctp29121982 on August 20, 2022, 09:28:34 AM
Thank you Liviu