FET Forum

FET Support (English) => General Stuff => Topic started by: morfeas on August 05, 2023, 05:23:31 PM

Title: A set of activities are overlapping
Post by: morfeas on August 05, 2023, 05:23:31 PM
HALLO!!!

First of all...
Thank you for this wonderful software!!!

I would like to ask if there is an option for 2 or more teachers , to have at the same period of time   their lessons in the timetable ?

I could not find something that works for this option...

In an other way you have a choice in FET
  ''time...activities....others 2....a set of activities are not overlapping ''   
if there was the choice of ''a set of activities are overlapping'' i could match the activities of each teacher in a tag and i could select this tags to overlapping with an other tag....
Is that possible somehow ?

Thank you very match!!!!
Title: Re: A set of activities are overlapping
Post by: Volker Dirr on August 05, 2023, 05:49:40 PM
By using "A set of activities occupies max time slots from a seletion".

add all activities from both (or more) teachers.
select all timeslots.
choose a value that is at least as big as the highest number of hours from a teacher.
If you think more closely about this constraint, you will notice that it is maybe too strict and might give problems with gaps.
So in normal case i recommend to use the higest "number of hours from a teacher + number of gaps per week"
Title: Re: A set of activities are overlapping
Post by: morfeas on August 05, 2023, 06:12:03 PM
THANK YOU VERY MUCH..I WILL TRY IT!!!!!
Title: Re: A set of activities are overlapping
Post by: YOUSSEF HOUIET on August 05, 2023, 06:59:19 PM
Use the constraint : a set of activities occupe max time slots, select all activities of the 2 or more teacher, then select all time solts of week,
in the field of max occupe, type : The maximum number of weekly working hours from among the teachers
Title: Re: A set of activities are overlapping
Post by: morfeas on August 05, 2023, 07:07:13 PM
I DID IT!! THANK YOU .IT WORKS PERFECT...