Hi,
I just started to use FET and got stuck. Could you please help me?
I have added an activity that should be scheduled multiple times during the week. Is there any other way to secure that, than to create as many copies of the given activity, as I want to use it per week.
Thanks very much
Ben
Hello, Ben,
Please increase the split in the add activity dialog :) This will also add automatically a constraint min days between activities constraint, as needed (you can see and edit this constraint in the constraints dialog).
Thanks a lot, man! Awesome stuff :)