FET Development => Suggestions => Topic started by: aries10 on August 08, 2025, 09:30:41 PM

Title: Modify % activities in time slots
Post by: aries10 on August 08, 2025, 09:30:41 PM
Hello, first of all, congratulations on all the work you've done. I'd like to suggest two changes to the activity constraints: the possibility to modify the percentage of the maximum or minimum number of activities in the selected time slots to allow for more solutions to be found. At the moment, the constraint is only at 100%. Thanks to everyone who wants to help me find a solution.
Title: Re: Modify % activities in time slots
Post by: Liviu Lalescu on August 09, 2025, 07:17:58 AM
Hello! Thank you!

Please confirm me that you refer to the constraints min/max simultaneous activities in selected time slots.

I will add your suggestion in the TODO. but unfortunately it is too difficult.
Title: Re: Modify % activities in time slots
Post by: aries10 on August 09, 2025, 08:09:43 AM
Yes,I confirm this. Thanks for your attention and assistance.