Hello,
I wonder if you could help me. Let say a subject has 2 sessions per week. If one session is the last lesson on one day, I want to avoid the other session being the first lesson the next day. There should be one or more of other lessons in between. Similar idea to min resting hrs. Is this possible?
Many thanks
Hello,
Maybe n_days_per_week-1 constraints activities pair of mutually exclusive time slots for each pair of activities. So math cannot be the last hour Monday and the first hour Tuesday.
Thank you. I couldn't find this constraint. Is it under Time>>Activity? Will I have to apply it to each activity? In fact I would like it to be for all activities that have more than one session. Thank you
Sorry I found it now as I upgraded to the latest version. It looks like I have to add each activity one by one and select each pair of day (Mon-Tue, Tue-Wed etc.) Is that correct? That is a lot of constraints as I actually want all activities to avoid slots like this. Thanks
You are welcome!
Please update to FET-7.8.0 and check the activities time constraints, Others (1), the 6th there.
Yes, unfortunately a lot of data inputting work...
I will add your suggestion to the TODO list. Maybe a suitable name and behavior for a possible new constraint could be devised.