Hola, Quisiera limitar que algunas actividades no puedan impartirse el mismo dia.
Hola!
Constraint min 1 days between activities, 100%.
Hola,
Muchas gracias por tu rapida respuesta pero entiendo que eso es para una misma actividad. En nuestro caso lo que queremos es que dos actividades no se impartan el mismo dia. Por ejemplo que Ingles y Lengua no puedan coincidir en el mismo dia.
Un saludo
Hola,
You are welcome!
If you have A1 (Id 12, John, English, 6A), A2 (Id 13, John, English, 6A), and A3 (Id 25, Brown, Spanish, 6A), you can add a constraint min 1 days 100% between (A1, A2, A3). You can add any (sub)activities in such a constraint.
You could also use other constraints, such as:
- Constraint students activity tag max 1 hours daily 100%.
- Constraint students max 1 activity tags per day from a set (Tag English, Tag Spanish).
I would prefer min days, it is the most efficient, but you might need more work to add the constraints for each desired group of activities.