In my university few classes can be taught on Saturdays, but most classes have to be on days from Monday to Friday. How can I indicate in FET that only some of the activities are available on Satudays?
I think you can use the activity(ies) preferred starting time(s).
Or maybe define some activity tags for the activities: MonFri or MonSat, and add constraints activities preferred starting times for each activity tag.
Thanks, I have figured out that I could also indicate available days for teachers too, like some of them can work on Saturdays and some not. I have built a small timetable for my department using FET, worked great. :)
and you can also do it with not available students (years/groups/or subgroups).
so if all groups of year 1 are not allowed to have school at saturday, then you just need to add a not available constraint to the year.
i think in most cases the not available constraint for students and teachers is the fastest solution.
Volker Dirr
yes, I agree with you :)