Messages - blusky78

#1
Hello,

than you for your help.

Just to give you mre context, we know that a small set of activities may not be possibile (say 10%) and that will be necessary to talk with teachers.
But, we'd like to get the whole timetable filled for what it is possibile, after then having a view of all impossible avtivities, then the persons in charge for this will contact the teachers, all the same week, necessary to close the midding activities.

And provided the timetable coming from FET, we'll give the tool to comlete the missing parts.

This is why we cannot provide juat a half timetable and cannot contact teachers one by one.

Thank you
#2
Hi,

thank you for your reply.
It seems, unfortunately, that for the time constraint for the teachers, it is not possibile to specify a weight less then 100% so it is not possible to let FET skip that activities.

I'm wondering if there is any workaround possibile.

Thank you,
#3
Hello,

we have setup a FET configuration file for an academy, with 360 activities, tens of teachers and classrooms.
Planning was stopping around at half of scheudling (200 activities) and then was hanging forever.
Later I discovered that just one teacher had the problem that her time constraints where too tight and had no time in week to attend all the assigned lessons.

Just letting more relaxed constraint on that teacher, resulted in the whole planning to be completed in 0 seconds.

I expected that FET could skip the problematic teacher and complete all the other activities that indeed could be planned regurarly. This would be a lot helpful to allow, later, to complete manually the missing activities.

Is there a way to make FET complete as much activities as possibile?

Thank you.