#1
I need at least 1 teacher free each period of the week, how can I do it?

I tried to do it making one group and a subject, and making the activity for that subject with all the teachers, but FET thinks that ALL of the teachers must be there, and I need ANY of the teachers to be. I cannot find the solution. Any suggestion?
#2
I don't know anything about that file format, but I guess it'll be possible to do it without changing that. Maybe a script checking the checkbox and executing a script to convert that checked checkbox to the constraints specified in #1 solution. That script will be executed when you push the Add Activity button.

Well, that's just an idea. You know what you're looking for and how to do it better than me, so you decide. I'll be using FET anyway. If you need some help from me, just let me know.
#3
Solution #1 works perfectly. Thanks.

Anyway, maybe it'll be useful to add a checkbox in the Add Activity dialog. That checkbox will say "Activity not in consecutive days".
#4
Thanks, I'm trying to do it right now. I'll tell you...
#5
Hi, normative for High-School in Spain specifies that if an activity is scheduled in 3 periods in a week, they can't be in three consecutive days. So if I set min n days between activities as 1, then sometimes I get the 3 activities in consecutive days. If I set it as 2, then a restriction must be broken as I only have 5 days and not always can be used Monday, Wednesday and Friday. Then sometimes I got two of these activities the same day.