placing activities consecutively by FET

Started by liquid, March 17, 2011, 10:43:31 PM

Previous topic - Next topic

0 Members and 1 Guest are viewing this topic.

liquid

Consider a split activity 2/5 - 1/5 - 1/5 - 1/5. FET places my 2 hour activity part in the same room. However in case of soft conflict when FET cannot place other 3 hours separately, it places them consecutively but not in the same room.
I might agree with FET in some cases when it cannot do desired split but if FET must join some activities consecutively let it do this in the same room. How to tell it to do in such way in case of soft conflict?

Liviu Lalescu

Unfortunately, there is no such option.

I added this in the TODO.

A possible solution: for such activities, remove them and add them as 2+2+1.

Liviu Lalescu

Reviving an old topic: this is possible with the constraint activities same room if consecutive.