Hi,

I need to make sure that certain activities don't happen on the same day. Is there anyway to do that?

Thanks,
Megan

Volker Dirr

FET -> Data -> time constraint -> activities -> min days between a set of activities

meganmassaro

Hi again,

That doesn't seem to be working.

I have all related activities grouped together (all of a grade's humanities meetings, etc.). For instance, 5th grade humanities has three different types of meetings:
HumSciDoub (in which it splits with science for 2 periods at a time)
HumDoub (a Humanities double)
Hum (a Humanities single period).

Humanities single periods should be both in the same day, and not the same day as a HumDoub or HumSciDoub.

Thanks again.

Liviu Lalescu

You could add more constraints min days between activities. But this might be complicated in your case, because you might need to add a constraint for each pair of activities.

You might consider the constraint students/teachers activity tag max 2 hours daily, after adding a tag "Humanities" to those activities.

ChicagoPianoTuner

Quote from: meganmassaro on May 08, 2017, 03:11:10 PM
Hi again,

That doesn't seem to be working.

I have all related activities grouped together (all of a grade's humanities meetings, etc.). For instance, 5th grade humanities has three different types of meetings:
HumSciDoub (in which it splits with science for 2 periods at a time)
HumDoub (a Humanities double)
Hum (a Humanities single period).

Humanities single periods should be both in the same day, and not the same day as a HumDoub or HumSciDoub.

Thanks again.

Hi Megan,