How to generate overlap

Started by Egoitz, July 01, 2025, 02:08:57 AM

Previous topic - Next topic

0 Members and 1 Guest are viewing this topic.

Egoitz

Dear,

We have some 3- or 4-hour activities for which we have a support teacher for 1 or 2 hours. We usually create a dummy activity and a dummy classroom for the support teacher, and we use the "two sets of activities have the same starting time (day + hour)" tool. However, it doesn't have to match only the start time; they could coincide at any time. How could we activate the overlapping option so they coincide at any time?

Thank you

Liviu Lalescu

Hello, Egoitz,

You could use a constraint activities occupy max time slots from selection: add the two activities, select all the slots of the week with X (red) and say max occupied = 3 or 4.