Started by Omar Ben Ali, September 10, 2017, 01:11:25 PM

Previous topic - Next topic

0 Members and 1 Guest are viewing this topic.

Omar Ben Ali

السلام عليكم

أتقاسم معكم هذا الملف الصعب

أتمنى تفاعلكم

البرنام يتوقف على بعد 3 مهام رغم  محاولات كثيرة لتخفيف القيود الزمانية والمكانية




Omar Ben Ali

ياليت الأخوة يقوموا بالتجربة لكن بنسخ قديمة من فيت

النسخة الاخيرة أعتقد أن بها مشكل

I think there is a problem with the last version of fet morocco

Liviu Lalescu

I think/hope/am convinced that there is not a problem when upgrading from FET-5.27.3-Morocco29 to FET-5.27.3-Morocco30. See the attached screen shot. They both reached maximum 937 and then went down, meaning that the data is probably too constrained.

Omar Ben Ali

 Thanks
I will try to lower some time constraints..

Omar Ben Ali

#4
I am sorry. I made a mistake. Indeed i added the constraint "Two activities grouped id=118 and id=119" to two subgroups of a set of students 1BL3 wich contradict the constraint "students  min hours daily  =2" and " students max gaps per week=0". This make the generation of the timetables impossible.
The question is why fet  remains four hours looking for an impossible timetable ?