change the place of one activity Without major changes in the other activities

Started by abdeljalil elghazoui, June 28, 2015, 05:51:03 PM

Previous topic - Next topic

0 Members and 1 Guest are viewing this topic.

abdeljalil elghazoui

At the end of the production time table
we sometimes want to change instead of an activity
But if we follow the normal route of fet its currency fully all activities
Is there is a way to change the place of this activity specifically
Without major changes in the other activities

A la fin de la production  du table de temps
nous voudrions  parfois  changer la place d'une activité
Mais si nous suivons la voie normale de fet  sa change entièrement  toutes les activités
Est-ce qu'il y a une façon de changer le lieu de cette  activité spécifiquement
Sans changements majeurs dans le reste des activités
"لا تهمني مشاكل العالم المهم أن لا أكون جزءا مساهما فيها"

Liviu Lalescu

Either:

1) Open from ~/fet-results/data_and_timetable.fet, then unlock a specific activity and regenerate;

or

2) After generating, select Advanced lock -> lock all activities of the current timetable. Then unlock a specific activity and regenerate.

But you may obtain an impossible timetable.

abdeljalil elghazoui

You're right, we can not get what we wanted
Is it possible for this to work  a new property under the name:

"a teacher's not available times withe the current  timetable"

as "not available times" are "the free hours withe the current  timetable"
And it will save in "a teacher's not available times"
And when we want to produce a new table we change a table for one teacher

"لا تهمني مشاكل العالم المهم أن لا أكون جزءا مساهما فيها"

Liviu Lalescu

I don't know if and when I will be able to do this. But I added it in the TODO.

Until then, I hope you can add teacher not available constraints by hand.

abdeljalil elghazoui

thank you a lot
And hopefully it will be soon
We also ask you for a similar property in Students set
It seems that these characteristics would be more effective
You can set the blank time
Although it is possible to move Activitys
For a teacher or more
Or for one Student set or for more
"لا تهمني مشاكل العالم المهم أن لا أكون جزءا مساهما فيها"

Liviu Lalescu

I added this also in the TODO. But it will not be soon, I am sorry.