I added this:

211---------------------------------------------------------
From dotosouza:

Since a min days between activities constraints with consecutive if same day true cannot place activities over a break, he suggests that the constraint
of type break to be removed from FET. Also because activities with duration >=2 cannot be split over a break. He had impossible timetable because
he didn't know this.

Or add a warning about this in the break time constraint dialog.
--------------------------------------------------------------

But I cannot add it in red bold  :) , because it is just the TODO file.

dotosouza

Lol... red and bAld xD

thanks dude.
I really hope you can put it in the dialog box

Liviu Lalescu

#32
OK, I have put this text in the constraints break dialog:

---
Note: An activity with duration greater than 1 cannot be split over a break. Also, the activities constrained by min days between activities constraints with 'consecutive if same day' = true cannot spread over a break.
---

I might change this text.

dotosouza

Quote from: Liviu Lalescu on February 06, 2015, 01:53:39 PM
Also, activities constrained by min days between activities constraints with 'consecutive if same day' = true cannot spread over a break.

They did spread over a break in my case, but it took ages for FET to do so.

And it was nearly impossible for the program to finish the timetables, because it was spending so much time trying to break the activities in different days while the teacher was supposed to come to school in only one day

Liviu Lalescu

#34
No, they won't spread, see the attached file.