miloudi

There is a problem in the constraint named ''' min days between activities''' There are studying materials of the same section twice or three times a day and this is a mistake, especially in materials shares 6 for each section or chapter..............Is there a solution to this problem with a special flag Algerian version

Liviu Lalescu

Please give us an example file to prove this.

miloudi

For example, we have regiments and sections 1 a 1 1 a 2 divide week to 10 periods, for example, Sunday morning Sunday evening ...Each period is divided into 4 hours .... Our material ...For example mathematics then 6 hours per week for each section or Regiment ....Required do not want to study, for example, section 1 a 1 math twice a day ....With science has experimented constraint min days between activities
But the program has stopped at a certain number

Liviu Lalescu

#3
I'm sorry, but I do not understand. Maybe somebody can translate for us, Arabic <-> English.

miloudi

The problem is we must not studying materials of less than 3 hours twice a day, for example of history should not be taught the students twice a day, for example Sunday 1 then Adersona Sunday 2 and this is wrong as well as in materials that have 6 hours or 5 hours like Arabic and French and mathematicsshould not be taught the same material section twice a day, for example, section 1 1 taught the French Sunday 1 then taught Sunday 2 and this is a mistake

http://arab4load.info/downloadf-2eaf13465431091-rar.html

Open the file version Algerian and you will understand what I mean

Volker Dirr

hmmm... so the days in min n day constraint must be calculated with modulo 2 div 2?

Liviu Lalescu

Quote
hmmm... so the days in min n day constraint must be calculated with modulo 2 div 2?

It is already calculated as it should be.

Liviu Lalescu

This is a screenshot from your activities. 7 activities, but only 4 are constrained. This must be changed as written in the FET help. Either add a new activity, or add new constraints. Remember that in min days constraints one FET day = one real day.