(Solved) About activate/deactivate activities

Started by Liviu Lalescu, June 09, 2008, 03:30:21 PM

Previous topic - Next topic

0 Members and 1 Guest are viewing this topic.

Liviu Lalescu

This is what I got today:

-----------
From Yush Yuen:

i am encountering a problem with de-activating
subjects. when i de-activate a set of activities belonging to a subject. all the time constrains would give errors and therefore cannot generate a timetable.

any way to get around that?
-----------

Indeed, all constraints referring to unactivated activities give errors. This is the first time I get this bug report (I didn't think of it).

Is this bug really important? I cannot think of a good method to solve it.

Liviu Lalescu

#1
QuoteThis is what I got today:

-----------
From Yush Yuen:

i am encountering a problem with de-activating
subjects. when i de-activate a set of activities belonging to a subject. all the time constrains would give errors and therefore cannot generate a timetable.

any way to get around that?
-----------

Indeed, all constraints referring to unactivated activities give errors. This is the first time I get this bug report (I didn't think of it).

Is this bug really important? I cannot think of a good method to solve it.

Edit: I solved this bug, the new 5.5.7 is ready now (11 June 2008).