Hi

I have to use two constraints: Max hours per morning and Max hours per afternoon for teacher.
But FET doesn't have these. Do you have any suggestion for us?

Thanks!


Liviu Lalescu

Hello,

You could use teacher(s) max hours per day (which refers to half days, FET days). Also, you could use more constraints of type activities occupy max time slots from selection.

If these are important, and if I were sponsored for them, I could try them.